| Month | Permits issued |
|---|---|
| January 2025 | 1,629 |
| February 2025 | 1,651 |
| March 2025 | 1,645 |
| April 2025 | 1,657 |
| May 2025 | 1,529 |
| June 2025 | 1,492 |
| July 2025 | 1,562 |
| August 2025 | 1,520 |
| September 2025 | 1,614 |
| October 2025 | 1,699 |
| November 2025 | 1,305 |
| December 2025 | 1,428 |
| January 2026 | 1,705 |
| February 2026 | 1,479 |
| March 2026 | 1,673 |
| April 2026 | 1,611 |
| May 2026 | 1,553 |
| June 2026 | 1,618 |
| July 2026 | 1,559 |
| August 2026 | 1,722 |
| September 2026 | 2,082 |
| October 2026 | 2,226 |
The busiest month in the last 12 was October 2026, with 2,226 permits.
Last 12 full months (November 2025 through October 2026). A permit that covers two job types is counted in both rows, so the rows add up to more than the city total above. Open a job type for its monthly trend, processing time and ZIP-level numbers.
| Job type | Permits, last 12 months | Jan–Oct change vs. prior year | Median days to issue | Median declared valuation |
|---|---|---|---|---|
| Re-roof | 11,550 | +23.2% | not enough dates | $5,200 |
| Kitchen and bath remodel | 3,673 | −5.5% | 21 days | $14,000 |
| ADU and room addition | 4,898 | −10.9% | 132 days | $93,019 |
Inside those groups: 2,112 permits mention a kitchen remodel and 2,970 a bathroom remodel (some mention both). 2,813 were ADU permits, 1,630 of them for new ADU construction, and 2,085 were room additions to single-family homes and duplexes.
Describe the job and we will pass it to up to four local pros, each with an active state license where one is required. You decide who to talk to.
Describe your project19,961 from November 2025 through October 2026, according to Los Angeles Department of Building and Safety (LADBS) open data. January through October 2026 was up 7.7% on the same months of 2025.
From November 2025 through October 2026: 91344 (580 permits), 91335 (497 permits), 90042 (465 permits).
October 2026, with 2,226 permits issued, the highest of the last 12 months.
Neighborhood links follow the busiest ZIP codes above, matched with our site’s ZIP-to-neighborhood map.
Example: reproduce the first job type’s count in the table above with this API query (each job page shows its own):
https://data.lacity.org/resource/pi9x-tg5x.json?%24select=count%28%2A%29&%24where=issue_date%3E%3D%272025-11-01%27+AND+issue_date%3C%272026-11-01%27+AND+permit_sub_type%3D%271+or+2+Family+Dwelling%27+AND+permit_type%3D%27Bldg-Alter%2FRepair%27+AND+%28upper%28work_desc%29+like+%27%25RE-ROOF%25%27+OR+upper%28work_desc%29+like+%27%25REROOF%25%27%29