ADU and Room Addition Permits in Los Angeles

How many ADU and room addition permits Los Angeles issued, how long they took, what owners declared as the job value and where the work is happening, computed from the city’s own permit records.

Updated November 17, 2026 · Source: Los Angeles Department of Building and Safety (LADBS) open data

The short version

4,898
ADU and room addition permits issued, November 2025 through October 2026
−10.9%
Jan–Oct 2026 vs. Jan–Oct 2025
132 days
Median time from submittal to issued permit
$93,019
Median declared permit valuation (not a price)

On this page

  1. Permits by month
  2. How long the permit takes
  3. Declared valuation
  4. Where the permits are
  5. FAQ
  6. Source and method

ADU and room addition permits issued per month in Los Angeles

Each bar is the number of ADU and room addition permits the Los Angeles Department of Building and Safety issued that month. Hover a bar for the exact count.

0100200300400500600January 2025: 453 permitsJan ’25February 2025: 505 permitsMarch 2025: 478 permitsApril 2025: 524 permitsApr ’25May 2025: 461 permitsJune 2025: 432 permitsJuly 2025: 490 permitsJul ’25August 2025: 466 permitsSeptember 2025: 415 permitsOctober 2025: 434 permitsOct ’25November 2025: 358 permitsDecember 2025: 388 permitsJanuary 2026: 403 permitsJan ’26February 2026: 452 permitsMarch 2026: 430 permitsApril 2026: 417 permitsApr ’26May 2026: 442 permitsJune 2026: 412 permitsJuly 2026: 403 permitsJul ’26August 2026: 384 permitsSeptember 2026: 383 permitsOctober 2026: 426 permitsOct ’26

Earlier monthsLast 12 months (November 2025 through October 2026)

Show the monthly numbers
MonthPermits issued
January 2025453
February 2025505
March 2025478
April 2025524
May 2025461
June 2025432
July 2025490
August 2025466
September 2025415
October 2025434
November 2025358
December 2025388
January 2026403
February 2026452
March 2026430
April 2026417
May 2026442
June 2026412
July 2026403
August 2026384
September 2026383
October 2026426

The busiest month in the last 12 was February 2026, with 452 permits.

How long an ADU and room addition permit takes in Los Angeles

Half of the 4,897 permits with both dates were issued within 132 days of submittal. The middle half took 70 to 256 days. 0.5% were issued the same day or the next day, and 8.6% within 30 days.

Declared permit valuation in Los Angeles

Across 4,895 permits with a declared value, the median was $93,019. The middle half fell between $50,000 and $150,000. The average, $123,840, sits above the median because a few large projects pull it up.

Declared valuation is the job value the applicant states on the permit application. It is not a contractor bid or a final cost, so use it to compare scopes, not as a price.

Split by type: new ADU construction permits had a median declared valuation of $122,000 (1,630 permits), and room additions $70,296 (2,083 permits).

Processing time differs too: a median of 165 days for new ADUs and 105.5 days for room additions.

Where Los Angeles homeowners pulled the most ADU and room addition permits

The ten ZIP codes with the most ADU and room addition permits, last 12 months. Medians are shown only where at least 10 permits have both dates (days) or 15 have a value (valuation).

ZIP codePermitsShareMedian days to issueMedian declared valuation
913441603.3%95.5$85,000
913351563.2%114$89,125
900661402.9%109$95,000
913311342.7%121.5$83,900
913671232.5%91$80,000
914061162.4%88.5$100,000
913521122.3%120$92,157
916061072.2%89$80,000
916051032.1%108$80,000
900451012.1%112$90,000

By community plan area

Los Angeles divides the city into 35 community plan areas. These had the most permits:

Community plan areaPermitsShareMedian days to issueMedian declared valuation
Northeast Los Angeles3417%200.5$91,607
Canoga Park-West Hills-Winnetka-Woodland Hills3356.8%94$80,000
West Adams - Baldwin Hills - Leimert2745.6%175.5$90,000
Van Nuys - North Sherman Oaks2615.3%107$100,000
Reseda - West Van Nuys2605.3%106.5$89,125
North Hollywood - Valley Village2485.1%107.5$95,735
South Los Angeles2394.9%165$94,500
Sun Valley - La Tuna Canyon2084.2%125.5$85,000
Wilshire1933.9%156$100,000
Palms - Mar Vista - Del Rey1873.8%109$100,000

Planning an ADU and room addition project in Los Angeles?

Describe the job and we will pass it to up to four local pros, each with an active state license where one is required. You decide who to talk to.

Describe your project

Frequently asked questions

How many ADU and room addition permits did Los Angeles issue in the last year?

4,898 from November 2025 through October 2026, according to Los Angeles Department of Building and Safety (LADBS) open data. January through October 2026 was down 10.9% on the same months of 2025.

How long does it take to get an ADU and room addition permit in Los Angeles?

Half of the 4,897 permits with both dates were issued within 132 days of submittal. The middle half took 70 to 256 days.

What do Los Angeles homeowners declare as the value of an ADU and room addition job?

The median declared permit valuation was $93,019, with the middle half between $50,000 and $150,000. Declared valuation is the value stated on the permit application; it is not a contractor price.

Which Los Angeles ZIP codes have the most ADU and room addition permits?

From November 2025 through October 2026: 91344 (160 permits), 91335 (156 permits), 90066 (140 permits).

Which month had the most ADU and room addition permits in Los Angeles?

February 2026, with 452 permits issued, the highest of the last 12 months.

Related pages

Find a pro

Neighborhood links follow the busiest ZIP codes above, matched with our site’s ZIP-to-neighborhood map.

Source and method

Reproduce the headline count with this API query:

https://data.lacity.org/resource/pi9x-tg5x.json?%24select=count%28%2A%29&%24where=issue_date%3E%3D%272025-11-01%27+AND+issue_date%3C%272026-11-01%27+AND+permit_sub_type%3D%271+or+2+Family+Dwelling%27+AND+%28%28permit_type+in+%28%27Bldg-New%27%2C%27Bldg-Addition%27%29+AND+use_desc+in+%28%27Accessory+Dwelling+Unit%27%2C%27Junior+Accessory+Dwelling+Unit%27%29+AND+NOT+%28upper%28work_desc%29+like+%27%25SUPPLEMENTAL%25%27+OR+upper%28work_desc%29+like+%27%25REVISION%25%27+OR+upper%28work_desc%29+like+%27%25WILDFIRE%25%27%29%29+OR+%28permit_type%3D%27Bldg-Addition%27+AND+use_desc+in+%28%27Dwelling+-+Single+Family%27%2C%27Duplex%27%29+AND+NOT+%28upper%28work_desc%29+like+%27%25ADU%25%27+OR+upper%28work_desc%29+like+%27%25ACCESSORY+DWELLING%25%27+OR+upper%28work_desc%29+like+%27%25SUPPLEMENTAL%25%27+OR+upper%28work_desc%29+like+%27%25REVISION%25%27+OR+upper%28work_desc%29+like+%27%25WILDFIRE%25%27+OR+upper%28work_desc%29+like+%27%25REBUILD%25%27%29%29%29