Kitchen and Bath Remodel Permits in Austin

How many kitchen and bath remodel permits Austin issued, how long they took and where the work is happening, computed from the city’s own permit records.

Updated November 17, 2026 · Source: City of Austin Development Services Department open data

The short version

551
Kitchen and bath remodel permits issued, November 2025 through October 2026
+1.7%
Jan–Oct 2026 vs. Jan–Oct 2025
19 days
Median time from submittal to issued permit

On this page

  1. Permits by month
  2. How long the permit takes
  3. Where the permits are
  4. FAQ
  5. Source and method

Kitchen and bath remodel permits issued per month in Austin

Each bar is the number of kitchen and bath remodel permits the City of Austin Development Services Department issued that month. Hover a bar for the exact count.

0204060January 2025: 36 permitsJan ’25February 2025: 43 permitsMarch 2025: 61 permitsApril 2025: 43 permitsApr ’25May 2025: 55 permitsJune 2025: 45 permitsJuly 2025: 48 permitsJul ’25August 2025: 48 permitsSeptember 2025: 41 permitsOctober 2025: 51 permitsOct ’25November 2025: 43 permitsDecember 2025: 29 permitsJanuary 2026: 36 permitsJan ’26February 2026: 48 permitsMarch 2026: 57 permitsApril 2026: 51 permitsApr ’26May 2026: 48 permitsJune 2026: 59 permitsJuly 2026: 47 permitsJul ’26August 2026: 60 permitsSeptember 2026: 36 permitsOctober 2026: 37 permitsOct ’26

Earlier monthsLast 12 months (November 2025 through October 2026)

Show the monthly numbers
MonthPermits issued
January 202536
February 202543
March 202561
April 202543
May 202555
June 202545
July 202548
August 202548
September 202541
October 202551
November 202543
December 202529
January 202636
February 202648
March 202657
April 202651
May 202648
June 202659
July 202647
August 202660
September 202636
October 202637

The busiest month in the last 12 was August 2026, with 60 permits.

How long a kitchen and bath remodel permit takes in Austin

Half of the 551 permits with both dates were issued within 19 days of submittal. The middle half took 3 to 56 days. 19.2% were issued the same day or the next day, and 59.5% within 30 days.

Where Austin homeowners pulled the most kitchen and bath remodel permits

The ten ZIP codes with the most kitchen and bath remodel permits, last 12 months. Medians are shown only where at least 10 permits have both dates (days) or 15 have a value (valuation).

ZIP codePermitsShareMedian days to issue
787456010.9%7.5
78731549.8%36
78757336%35
78759336%22
78749336%33
78704325.8%58.5
78703315.6%48
78748254.5%6
78750213.8%6
78723213.8%16

Planning a kitchen and bath remodel project in Austin?

Describe the job and we will pass it to up to four local pros, each with an active state license where one is required. You decide who to talk to.

Describe your project

Frequently asked questions

How many kitchen and bath remodel permits did Austin issue in the last year?

551 from November 2025 through October 2026, according to City of Austin Development Services Department open data. January through October 2026 was up 1.7% on the same months of 2025.

How long does it take to get a kitchen and bath remodel permit in Austin?

Half of the 551 permits with both dates were issued within 19 days of submittal. The middle half took 3 to 56 days.

Does Austin permit data show what a kitchen and bath remodel costs?

No. Of 9,033 residential building and driveway permits issued from November 2025 through October 2026, only 273 list a job valuation above $1,000, and 3,821 list exactly $1. That is too thin to report a cost, so this page does not.

Which Austin ZIP codes have the most kitchen and bath remodel permits?

From November 2025 through October 2026: 78745 (60 permits), 78731 (54 permits), 78757 (33 permits).

Which month had the most kitchen and bath remodel permits in Austin?

August 2026, with 60 permits issued, the highest of the last 12 months.

Related pages

Find a pro

Source and method

Reproduce the headline count with this API query:

https://data.austintexas.gov/resource/3syk-w9eu.json?%24select=count%28%2A%29&%24where=issue_date%3E%3D%272025-11-01%27+AND+issue_date%3C%272026-11-01%27+AND+permit_class_mapped%3D%27Residential%27+AND+permit_type_desc%3D%27Building+Permit%27+AND+work_class+in+%28%27Repair%27%2C%27Remodel%27%2C%27Addition+and+Remodel%27%29+AND+%28upper%28description%29+like+%27%25KITCHEN%25%27+OR+upper%28description%29+like+%27%25BATHROOM+REMODEL%25%27+OR+upper%28description%29+like+%27%25BATH+REMODEL%25%27+OR+upper%28description%29+like+%27%25REMODEL+BATHROOM%25%27+OR+upper%28description%29+like+%27%25REMODEL+OF+BATHROOM%25%27+OR+upper%28description%29+like+%27%25REMODEL+THE+BATHROOM%25%27+OR+upper%28description%29+like+%27%25TUB+TO+SHOWER%25%27+OR+upper%28description%29+like+%27%25TUB-TO-SHOWER%25%27+OR+upper%28description%29+like+%27%25SHOWER+CONVERSION%25%27%29